Week 69, Day 2

Week 69, Day 2:

  • More work on the stone cladding
  • More work on the waterproof coverings for the door canopies
  • Installation of shower screens in 3 of the bathrooms by Alvaston Glass (that’s their van in the photo)
    • Most of the work is complete but there are some loose ends to sort out in a few days – like hanging the shower doors
Week 69, Day 2

Week 69, Day 2

Shower screen in Bedroom 2 En-Suite

Week 68, Day 2

Week 68, Day 2:

  • More work on the door canopies, preparing to install the permanent waterproof membranes in place of the temporary polythene sheeting
  • Further progress on the preparations for the 14 low-level outside lights, which will be mounted on top of the stone cladding with their cables hidden within the cladding
Week 68, Day 2

Week 68, Day 2

Wiring for 1 of 14 outside wall lights (Nordlux Canto)