Week 45, Day 1

Week 45, Day 1:

  • A busy day with lots of people on site
  • Tidying up the field which was dug up for the Ground Source Heat Pump collector pipe trenches, now that the soil has had chance to settle
  • Lots of work on the plumbing – sorting out the water and waste for the island sink, piping up the duct heater in the MVHR system, installing another bathroom basin, piping up the remaining shower control boxes etc.
  • More second-fix electrical, mostly more lighting fixtures
  • Applying protective oil to the cedar boards on the solar shading, to match the cedar cladding elsewhere, and then putting a first coat of oil on some of the oak flooring
  • Sanding the rest of the oak flooring ready for oiling
Week 45, Day 1

Week 45, Day 1

Field to west of house levelled out with the weeds scraped off

Field to west of house levelled out with the weeds scraped off

Cedar boards of solar shading treated with Osmo oil

Cedar boards of solar shading treated with Osmo oil

Downlights in Master Bedroom rotated so they shine vertically despite the 30 degree roof pitch

Downlights in Master Bedroom rotated so they shine vertically despite the 30 degree roof pitch

Week 44, Day 5

Week 44, Day 5:

  • Grouting of some of the bathroom tiles
  • Finishing the installation of the internal doors
  • More skirting boards and architraves
  • More second-fix electrical, mostly installing more of the downlights on the First Floor
Week 44, Day 5

Week 44, Day 5

Grouted tiles in the First Floor Bathroom

Grouted tiles in the First Floor Bathroom

The last of the internal doors - from the Hallway to the Kitchen

The last of the internal doors – from the Hallway to the Kitchen

Downlights in the Master Bedroom

Downlights in the Master Bedroom