Week 44, Day 4

Week 44, Day 4:

  • Lots of work on the ventilation system
    • Installing the warm-water Duct Heater into the supply duct in the Plant Room
    • Completing most of the other ducting in the Plant Room
    • Installing most of the air valves in the various rooms
  • More second-fix electrical, including installing the DIN rail boxes for the lighting controls on the First Floor
  • More work on the skirtings, architraves and window boards
Week 44, Day 4

Week 44, Day 4

Duct heater installed in Plant Room

Duct heater installed in Plant Room

Air extract valve in a Bathroom

Air extract valve in a Bathroom

Starting to bring order to chaos in the main control panels

Starting to bring order to chaos in the main control panels

Week 44, Day 3

Week 44, Day 3:

  • Completion of the Solar Shading (the round-the-corner section at the far left of the main photo)
  • More electrical second-fix, including connecting the Induction Hob (which had been waiting on the replacement island worktop), lots more sockets and the start of work on the electrical boards on the First Floor
  • More skirtings, architraves and internal window boards
Week 44, Day 3

Week 44, Day 3

Solar shading at the south-west corner

Solar shading at the south-west corner

Day 1 of installing the electrical boards on the First Floor

Day 1 of installing the electrical boards on the First Floor