Over the weekend I started commissioning the kitchen appliances – cleaning them and running their “first use” programmes, and cleaning the kitchen cupboards and starting to remove the blue protective film
I also fitted two of the ceiling speakers (in the kitchen) and hooked up a small amplifier to test them, and they’re working fine
With the inside tidied and some decent weather the team spent most of the day tidying up the outside so now it looks a lot better in the overview shot
I spent the evening installing the LED lighting strips in the Ground Floor WC so those are now working from the PIR sensor