Week 31, Day 4

Week 31, Day 4:

  • If you look carefully you can see a change in the overview photo – the timber cladding is now installed along about half of the southern elevation
  • Buffing the polished concrete floor, once it had dried following yesterday’s wet grinding
  • Installing the plasterboard in the Communications Room (basically a cupboard off the Office on the second floor, over the balcony, where all the data cables run back to)
  • More electrical and plumbing first-fix
Week 31, Day 4

Week 31, Day 4

Polished concrete floor

Polished concrete floor in Open Plan area

Pink FireLine plasterboard in the Communications Room

Pink FireLine plasterboard in the Communications Room

 

Week 31, Day 3

Week 31, Day 3:

  • Wet diamond-grinding the concrete floor, taking off 1-2mm to remove the crazing on the top surface and exposing some of the sand grains (see tomorrow for a photo)
  • Completing the timber cladding on the eastern elevation
  • More progress on the plastering, mainly in the Plant Room
Week 31, Day 3

Week 31, Day 3

Timber cladding completed on the east elevation

Timber cladding completed on the east elevation

Skim coat of plaster over the FireLine boards in the Plant Room

Skim coat of plaster over the FireLine boards in the Plant Room