Another public holiday (for ‘May Day’) so no work on site. Photo shows the status as of the end of Week 8.

Another public holiday (for ‘May Day’) so no work on site. Photo shows the status as of the end of Week 8.

Good progress with the concrete blockwork walls. Five courses is as high as they’re going for now (they’ll go higher once there’s some scaffolding up – after the cavity insulation and the outer skin of bricks have been added).