Today’s progress mostly consisted of excavating another metre or so of ground all around the building, which will get a layer of stone to provide a solid base for the scaffolding (and stop things getting too muddy in the inevitable wet weather).

Today’s progress mostly consisted of excavating another metre or so of ground all around the building, which will get a layer of stone to provide a solid base for the scaffolding (and stop things getting too muddy in the inevitable wet weather).

Not much visible progress evident in the photo, but there was a delivery of dry-mix concrete which got carefully loaded into the wall cavity below DPC, and the start of more excavation around the site.