Outbuildings: Week 4, Day 3

Outbuildings: Week 4, Day 3

More of the same as yesterday, finishing up the below-DPC walling on the garages, off to the left of the overview shot.

The large digger and dumper used previously had been collected a few days ago, but a smaller digger and dumper were delivered since there’s a bit more excavation required around the outside of the walls to provide a good base for the scaffolding – and there is a layer of stone to be spread and compacted as a base for the insulation under the floor slabs.

Outbuildings: Week 4, Day 2

Outbuildings: Week 4, Day 2

More work on the below-DPC walling for the garages, out of shot to the left, together with some more fiddly tasks like installing the in-slab drain pipes and ducts for the incoming electrical supply.

The automated post numbering was showing today as “Week 4, Day 1” (rather than “Day 2”) so I’ve tweaked the starting date to (hopefully) fix that from now on.