Week 38, Day 2

Week 38, Day 2:

  • The team from Contrasol were back on site to install the steel support brackets for the brise soleil
    • The large expanse of glazing on the south elevation in particular is good for natural light and passive solar gain in the winter but potentially introduces a risk of overheating in the summer
    • A horizontal brise soleil just above the sliding doors blocks the high-level sun in mid summer but allows the lower winter sun through underneath
    • The exact projection of the brise soleil was included in the PHPP calculations to take account of both the passive solar gain and the risk of overheating
  • The first of the wet plaster on the masonry walls
    • Almost all of the rooms have at least one masonry wall
    • The external walls are wet-plastered to form the main air tightness barrier
    • While the internal masonry walls could be plasterboarded (with dot-and-dab fixings) most of them are also wet plastered, which is better for thermal mass
Week 38, Day 2

Week 38, Day 2

Steel support brackets for Contrasol brise soleil above sliding doors on the south and west elevations

Steel support brackets for Contrasol brise soleil above the sliding doors on the south and west elevations

Base coat of wet plaster on the masonry outer wall in Bedroom 3

Base coat of wet plaster on the masonry outer wall in Bedroom 3

Finish coat of wet plaster on an internal masonry wall in Bedroom 3

Finish coat of wet plaster on an internal masonry wall in Bedroom 3

Week 38, Day 1

Week 38, Day 1:

  • I didn’t spot the disk on the Raspberry Pi computer which grabs the hourly snapshots went full at noon so the evening shots are missing and hence the automated Posting logic didn’t work properly. The photo here is from 12:39 – not even on the hour. Should all be fixed now.
  • More electrical first-fix – installing the remaining plaster light housings in the kitchen and preparing some trunking for the incoming mains cable.
  • More plastering, boarding out the stud-work in the open plan area.
  • Some more joinery – such as installing the door frames (which have been going in over recent days but without any photos until now)
Week 38, Day 1

Week 38, Day 1

Plaster ceiling light fittings over the kitchen sink

Plaster ceiling light fittings over the kitchen sink

Plasterboard in the south-west corner of the open plan area

Plasterboard in the south-west corner of the open plan area

Door frame - this one is between the Kitchen and the Utility Room

Door frame – this one is between the Kitchen and the Utility Room