Week 54, Day 3

Week 54, Day 3:

  • Quite a busy day with good progress on electrical and plumbing second-fix
  • The most notable progress was with the glass balustrades for the staircases which are about 2/3 installed and should be finished tomorrow
Week 54, Day 3

Week 54, Day 3

Alvaston Glass installing the first section of glass balustrade on the first-to-second floor staircase

Alvaston Glass installing the first section of glass balustrade on the first-to-second floor staircase

Glass balustrade for Second Floor landing

Glass balustrade for Second Floor landing

Week 54, Day 2

Week 54, Day 2:

  • Installation of the Phone Line into the house, using the armoured cable previously routed from the Comms room to the underground joint box outside
    • This isn’t operational yet due to a fault on the line between the Distribution Point and the Cabinet which should be fixed within a day or two
  • Laying the rubber tiles over their underlay on the balcony
    • These are Eurodec Premier Rubber Tiles in grey which protect the Sarnafil single-ply membrane beneath while allowing water to drain though
Week 54, Day 2

Week 54, Day 2

Eurodec Premier Rubber Tiles on balcony floor

Eurodec Premier Rubber Tiles on balcony floor