Video Summary, Weeks 10 – 20

Now the roof is on I reckon it’s time for another time-lapse video. I decided to mix things up a bit and post the view from the second camera which started recording in Week 10. Once the build is finished I’ll post the full videos from both cameras.

As before, the video is hosted on YouTube; it’s 1:22 long.

Sundays are excluded again but otherwise there’s a frame on the hour every hour during “daylight”. Compared to the main camera position this one struggles a lot more with facing into the sun which makes it more difficult to automatically define “daylight” so there are a few dark frames here and there.

I moved the camera to point a bit higher on 2016-02-17 to ensure it captures the whole of the final building.

Week 20, Day 5

Week 20, Day 5:

  • Finishing touches to the support structure for the “roof” over the north elevation of the first floor and installation of most of the covering boards
Week 20, Day 5

Week 20, Day 5

Boarding the "roof" on the north elevation of the first floor

Half-way through boarding the “roof” on the north elevation of the first floor

Mostly finished with the boarding

Mostly finished with the boarding

Close-up view of the finished structure

Close-up view of the two layers of timber and board

Wider view from the main camera location

End-of-day view from the main camera location

I don’t often post photos showing the house from the north-east, so here’s one now.

End-of-day view from the north-east

End-of-day view from the north-east