Week 54, Day 2

Week 54, Day 2:

  • Installation of the Phone Line into the house, using the armoured cable previously routed from the Comms room to the underground joint box outside
    • This isn’t operational yet due to a fault on the line between the Distribution Point and the Cabinet which should be fixed within a day or two
  • Laying the rubber tiles over their underlay on the balcony
    • These are Eurodec Premier Rubber Tiles in grey which protect the Sarnafil single-ply membrane beneath while allowing water to drain though
Week 54, Day 2

Week 54, Day 2

Eurodec Premier Rubber Tiles on balcony floor

Eurodec Premier Rubber Tiles on balcony floor

Week 51, Day 4

Week 51, Day 4:

  • Installing the remaining inspection chambers, connecting up the drains and supporting them in concrete so they stay in position during back-filling of the trenches
  • Finishing touches on the Ground Source Heat Pump installation, insulating the remaining fittings and topping up the brine circuit after it’s been running for a while and the automatic air vents have bled out most of the air (with a consequent reduction in operating pressure)
Week 51, Day 4

Week 51, Day 4

Drains to the west of the house

Drains to the west of the house

Drains to the east of the house

Drains to the east of the house