Week 53, Day 4

Week 53, Day 4:

  • Nearing completion on the second-fix plumbing, with all the heating systems now operational and good progress on the remaining sinks and taps
  • As the build nears completion the focus is switching more to cleaning and tidying rooms once all the work in them has been completed
Week 53, Day 4

Week 53, Day 4

Vanity top and sink installed in First Floor bathroom

Vanity top and sink installed in First Floor bathroom

Week 52, Day 2

Week 52, Day 2:

  • Patching the holes in the plasterboard made when adjusting the staircase treads
  • Delivering a batch of the oak boxes for the stair treads
  • Insulating the rest of the duct work in the Plant Room
Week 52, Day 2

Week 52, Day 2

Oak boxes for stair treads stacked in hallway

Oak boxes for stair treads stacked in hallway

MVHR supply duct work now fully insulated in Plant Room

MVHR supply duct work now fully insulated in Plant Room