Week 45, Day 4

Week 45, Day 4:

  • MVHR commissioning by Steve from the Green Building Store, adjusting all the air valves to deliver the correct flow rates and setting the Low, Medium and High fan speeds
  • More second-fix on the intruder and fire alarm system, installing the control panel, keypad etc.
  • More second-fix electrical, including installing some of the wall lights
  • More work on the door furniture, including the lock on the Plant Room door
Week 45, Day 4

Week 45, Day 4

Intruder alarm box on the west elevation

Intruder alarm box on the west elevation

Week 44, Day 4

Week 44, Day 4:

  • Lots of work on the ventilation system
    • Installing the warm-water Duct Heater into the supply duct in the Plant Room
    • Completing most of the other ducting in the Plant Room
    • Installing most of the air valves in the various rooms
  • More second-fix electrical, including installing the DIN rail boxes for the lighting controls on the First Floor
  • More work on the skirtings, architraves and window boards
Week 44, Day 4

Week 44, Day 4

Duct heater installed in Plant Room

Duct heater installed in Plant Room

Air extract valve in a Bathroom

Air extract valve in a Bathroom

Starting to bring order to chaos in the main control panels

Starting to bring order to chaos in the main control panels