Week 17, Day 1

Week 17, Day 1:

  • Yet another wet day.
  • Anvil Hire delivered a digger ready for excavating the trenches for the service connections to the house (electricity and water) which was used to tidy up some of the rougher areas around the site.
  • Various other clearing and cleaning activities, given the weather. The beam and block floor got covered with a rough layer of mortar while the blocks were being laid which needs to be cleared off before laying the floor insulation, so some progress made with that.
Week 17, Day 1

Week 17, Day 1

Week 16, Day 5

Week 16, Day 5:

  • More work on the second floor boards
Week 16, Day 5

Week 16, Day 5

I’ve only been at home for a couple of days in the past two weeks so I don’t have many photos of the progress on the second floor. Here are a couple showing the second floor structure and boarding, using the same approach as for the first floor.

Second floor structure under home office

Second floor structure under home office

Second floor structure above north-east bedroom

Second floor structure above north-east bedroom