Week 55, Day 3

Week 55, Day 3:

  • A site meeting with the Architects, starting to create a list of “snagging” items for the interior and to agree the way forward for the Retaining Wall to the north of the house
  • More work on the oak boards which will cover the fixings for the glass balustrades on the landings (rather than on the stair steps)
  • Finally taking delivery of the correct “Swiss Round” lock cylinder for the front door, 7 months after the door was installed
    • This has been something of a saga with the main lesson being that if someone at the door supplier mistakenly specifies a “Round” (rather than a “Euro”) cylinder on an Internorm door – especially one with electric locking – then get that corrected before the order is placed
Week 55, Day 3

Week 55, Day 3

Fixings for glass balustrades on landings

Fixings for glass balustrades on landings

"Swiss Round" door lock cylinder in front door

“Swiss Round” door lock cylinder in front door

 

Week 36, Day 1

Week 36, Day 1:

  • A site meeting with the Architect to agree the revised specification for the Zinc Roof and its Structured Underlay
    • This is now agreed but Full Metal Roofing need to finish another large project first so they won’t be starting work for a couple of weeks
  • More progress on the plastering, finishing off the walls in the Office and other areas on the Second Floor
  • More progress on the Plant Room pipework
  • The tele-handler was off-hired
Week 36, Day 1

Week 36, Day 1

Plaster skim coat complete on the walls in the Office

Plaster skim coat complete on the walls in the Office

Alcove in the Second Floor Bathroom

Alcove in the Second Floor Bathroom

Concealed cistern in the Master Bedroom En-Suite

Concealed cistern in the Master Bedroom En-Suite