Week 36, Day 1

Week 36, Day 1:

  • A site meeting with the Architect to agree the revised specification for the Zinc Roof and its Structured Underlay
    • This is now agreed but Full Metal Roofing need to finish another large project first so they won’t be starting work for a couple of weeks
  • More progress on the plastering, finishing off the walls in the Office and other areas on the Second Floor
  • More progress on the Plant Room pipework
  • The tele-handler was off-hired
Week 36, Day 1

Week 36, Day 1

Plaster skim coat complete on the walls in the Office

Plaster skim coat complete on the walls in the Office

Alcove in the Second Floor Bathroom

Alcove in the Second Floor Bathroom

Concealed cistern in the Master Bedroom En-Suite

Concealed cistern in the Master Bedroom En-Suite

Week 28, Day 3

Week 28, Day 3:

  • Architects site meeting #06
    • Looks like we might have a way forward with the zinc roof build-up that will enable the zinc roof installation to proceed
  • More progress on the cedar cladding on the west elevation, now up to the under-side of the main roof
  • More progress on the first-fix for the electrics and the plumbing:
    • White wires are for the intruder / fire alarm system
    • Green wires are specific KNX cables which will enable the “dumb” light switches to be replaced with fully-fledged KNX switches in due course
Week 28, Day 3

Week 28, Day 3

Cedar cladding up to main roof on west elevation

Cedar cladding up to main roof on west elevation

Cedar cladding boards carefully cut around zinc roof covering

Cedar cladding boards carefully cut around zinc roof covering

One of the light switches, wired using green KNX cable

One of the light switches, wired using green KNX cable

Plant room wall boarded with plywood and taped airtight membrane

Plant room wall boarded with plywood and taped airtight membrane