Week 51, Day 4

Week 51, Day 4:

  • Installing the remaining inspection chambers, connecting up the drains and supporting them in concrete so they stay in position during back-filling of the trenches
  • Finishing touches on the Ground Source Heat Pump installation, insulating the remaining fittings and topping up the brine circuit after it’s been running for a while and the automatic air vents have bled out most of the air (with a consequent reduction in operating pressure)
Week 51, Day 4

Week 51, Day 4

Drains to the west of the house

Drains to the west of the house

Drains to the east of the house

Drains to the east of the house

Week 48, Day 1

Week 48, Day 1:

  • A relatively quiet day since only a few of the build team were on-site for most of the time
  • Some more progress connecting up the drains (just visible at the right of the overview shot)
  • More second-fix electrical, including installing the array of wall lights in the Master Bedroom (photo below)
Week 48, Day 1

Week 48, Day 1

Wall lights in the Master  Bedroom

Wall lights in the Master Bedroom

This photo doesn’t do the wall lights justice – they’re the Theo model from Qazqa so see that site for more info. Watch out for a better photo when the rest of the wall has been painted and the lights are all on.