Week 46, Day 5

Week 46, Day 5:

  • More second-fix – door stops and some more lighting fixtures
  • More tiling – notably the wall tiles in the Ground Floor Shower Room
  • An initial air-tightness test which showed we’re a little short of the Passivhaus requirement of 0.6, with a reading of around 1, so some more work to do there
Week 46, Day 5

Week 46, Day 5

Wall tiles in the shower for the Ground Floor Shower Room

Wall tiles in the shower for the Ground Floor Shower Room

Air pressure test

Air pressure test

Week 46, Day 4

Week 46, Day 4:

  • Progress on the floor and wall tiling, preparing the wet-room floor in the Ground Floor shower room and tiling in the Master Bedroom En-Suite
  • More work on the foul water drainage
  • Final preparations for the air pressure test (scheduled for tomorrow) – sealing the area where most of the pipes enter the building in the Utility Room, and fitting the Cat Flap
  • Commissioning the intruder and fire alarm systems – testing all the sensors and programming via the keypad
Week 46, Day 4

Week 46, Day 4