Week 46, Day 2

Week 46, Day 2:

  • Laying the new telephone cable to the underground joint box to the north-west of the house
  • Clearing the area to the east of the house, locating the water supply pipe and digging trenches for the foul drainage connection to the Biorock treatment system
Week 46, Day 2

Week 46, Day 2

Digging the drainage trenches

Digging the drainage trenches

Week 7, Day 5

Week 7, Day 5:

  • Still more progress cutting and fitting the blocks for the ground floor
    • The south-east corner (nearest the camera) is missing two concrete beams which for some reason were not included in the original delivery, but apart from that section the floor is now complete
    • The missing beams are due for delivery on Monday (Week 8, Day 1)
  • Installation of the remaining sections of oversite concrete, for the Utility Room and the Shower Room
  • Lots of deliveries:
    • Another load of concrete blocks, for the walls above the ground floor
    • The wooden floor joists and boards for the first and second floors, stacked out of sight on the floor of the old cow shed – these were supplied by Harlow Timber Systems
Week 7, Day 5

Week 7, Day 5

That’s me (dMb) again, in the hi-vis rain jacket near the middle of the frame.

Beam and block floor under kitchen - darker blocks are 3.6N and paler ones are 7.3N

Beam and block floor under kitchen – darker blocks are 3.6N and paler ones are 7.3N, required where the walls continue through the floor