Week 31, Day 4

Week 31, Day 4:

  • If you look carefully you can see a change in the overview photo – the timber cladding is now installed along about half of the southern elevation
  • Buffing the polished concrete floor, once it had dried following yesterday’s wet grinding
  • Installing the plasterboard in the Communications Room (basically a cupboard off the Office on the second floor, over the balcony, where all the data cables run back to)
  • More electrical and plumbing first-fix
Week 31, Day 4

Week 31, Day 4

Polished concrete floor

Polished concrete floor in Open Plan area

Pink FireLine plasterboard in the Communications Room

Pink FireLine plasterboard in the Communications Room

 

Week 31, Day 2

Week 31, Day 2:

  • More first-fix
  • Routing some of the semi-rigid ventilation ducts for the MVHR system, relatively easy using the plastic ducts and with the Easi-Joists but still something of a challenge in the more congested areas
Week 31, Day 2

Week 31, Day 2

All the ventilation ducts need to pass through the Second Bedroom ceiling

All the ventilation ducts need to pass through the Second Bedroom ceiling

Some of the rooms require twin ducts to carry the required flow rate

Some of the rooms require twin ducts to carry the required flow rate