Week 26, Day 4 Posted on 2016-04-14 by dMb Reply Week 26, Day 4: Framing the stud-work partitions for the first-floor bathrooms Starting the electrical first-fix, for the sockets on the second floor Week 26, Day 4 En-suite Bathroom for the Guest Suite Electrical first-fix on the second floor (Bedroom 5) Temporary polythene cover for the office window
Week 25, Day 6 Posted on 2016-04-09 by dMb Reply Week 25, Day 6: Another working Saturday, getting ready for the concrete slab on the ground floor Underfloor heating pipe installation Electrical floor box installation Air-tight taping the damp proof membrane under the concrete Week 25, Day 6 Completed Underfloor Heating pipework in Open-Plan Area Completed Underfloor Heating pipework in Hallway Underfloor Heating Manifold Electrical floor box, one of two in the Open-Plan Area Electrical floor boxes in Living Room Air tight pipe grommet