Week 47, Day 1

Week 47, Day 1:

  • Not much is changing on the outside view at the moment but there’s been a subtle change today- the two rainwater down-pipes have been installed on the south elevation, draining the concealed gutter just below the solar panels – there’s a better view in the wider shot further down
  • More work on the tiling – notably the floor tiles for the wet-room shower in the Ground Floor Shower Room
Week 47, Day 1

Week 47, Day 1

Wider view from the main camera location

Wider view from the main camera location

Floor tiles (not yet grouted) in the Ground Floor Shower Room

Floor tiles (not yet grouted) in the Ground Floor Shower Room

Week 45, Day 3

Week 45, Day 3:

  • Close to completion on the kitchen installation, with the hob now sealed to the Silestone worktop with heat-resistant silicone and the pop-up power sockets installed in the island worktop
  • The first day of second-fix on the security and fire alarm systems, installing some of the movement and shock sensors
  • More second-fix electrical, installing the last of the PIR sensors for the lights in some of the ground floor rooms
  • More work on the internal doors, drilling out for the door handles and latches
Week 45, Day 3

Week 45, Day 3

Second Floor Landing complete apart from paintwork

Second Floor Landing complete apart from paintwork and staircase balustrade

PIR movement sensor and shock sensor on door frame

PIR movement sensor and shock sensor on door frame