Week 60, Day 1

Week 60, Day 1:

  • Some visible progress on the overview shot for the first time in a while – the area under what will be the terrace to the south of the house has been filled with MOT1 stone and compacted
  • Most of the large pile of soil excavated from the house foundations has now been used to level out the ground to the west of the house and also to the north-east of the plot (where the Biorock sewage plant is raised out of the ground)
Week 60, Day 1

Week 60, Day 1

The large pile of soil that's been west of the caravan for over a year has now gone

The large pile of soil that’s been west of the caravan for over a year has now gone

Soil moved to level the area beyond the Biorock unit

Soil moved to level the area beyond the Biorock unit

 

Week 59, Day 5

Week 59, Day 5:

  • Quite a busy day finishing off various jobs on the inside and some of the landscaping on the outside
  • Patching up the plasterboard removed to apply the air tightness tape
  • Tiling the floor in the Utility Room
  • Filling the planting beds which are part of the Retaining Wall on the north side with topsoil
Week 59, Day 5

Week 59, Day 5

Rubber floor tiles in Utility Room

Rubber floor tiles in Utility Room

Topsoil in planting beds on north side

Topsoil in planting beds on north side