Week 58, Day 5

Week 58, Day 5:

  • More progress on the ground works, back-filling behind the retaining wall and in the planters and levelling out the area by the side entrance
    • The lower section of retaining wall will be planted with ground-cover plants, and so it needs filling with topsoil and not the MOT 1 stone which can be seen in the photo, which will have to be dug out and replaced
    • This wall also needs lowering by one course of blocks so it lines up correctly with the middle step
  • A little more work on the outdoor electrics, setting galvanized steel conduit boxes into the blockwork and wiring the SWA cable into those for the outside lights and sockets
    • Most of the cables will be covered by the stone cladding
Week 58, Day 5

Week 58, Day 5

Back-filled retaining wall

Back-filled retaining wall

Levelled area by side door

Levelled area by side door

Cable boxes for outdoor lights and power sockets

Cable boxes for outdoor lights and power sockets

Week 45, Day 2

Week 45, Day 2:

  • More work on the landscaping, levelling out the rubble remaining from the demolition of the old barns to form a parking area by the (future) garages
  • Lots more second-fix electrical, including starting to wire up the control boards for the lighting and window blinds
  • Applying the oil finish to the oak flooring – second coat on the Second Floor (Office and Landing) and first coat on the Ground Floor (Living Room and Dining Room)
  • Adding some of the insulation to the MVHR ducts
    • The Intake and Exhaust ducts will be carrying air at “outside” temperature to the MVHR unit, through the “internal” air in the Plant Room – so there’s a risk of condensation and they need to be heavily insulated (even though the ducts themselves are made of expanded polystyrene)
  • More work on the skirting boards, architraves and internal doors
Week 45, Day 2

Week 45, Day 2

Rubble from old barns levelled out to form parking area

Rubble from old barns levelled out to form parking area

KNX and DALI control boards on the First Floor

KNX and DALI control boards on the First Floor

First coat of oil finish on the oak flooring in the Living Room

First coat of oil finish on the oak flooring in the Living Room

Second coat of oil finish on the oak flooring in the Home Office

Second coat of oil finish on the oak flooring in the Home Office

Partially completed insulation on the Intake and Exhaust MVHR ducts

Partially completed insulation on the Intake and Exhaust MVHR ducts