Outbuildings: Week 24, Day 3

Outbuildings: Week 24, Day 3

More progress on the roof tiling, completing the South-facing section of the Garage roof then moving back to progress the North-facing section – and good progress with the first-fix electrical installation (although there’s an element of second-fix happening too, since the usual requirement to wait for plastering and plasterboard installation etc. doesn’t apply to this non-domestic building).

Outbuildings: Week 24, Day 2

Outbuildings: Week 24, Day 2

More progress on the roof tiling – above and to the left of the solar PV array.

Roof tiling completed around the solar PV array and progressing towards the West gable of the South-facing roof

Multiple deliveries too – another 2,000 roof tiles and the rainwater goods.

Then also the first day of first-fix on the electrical installation.