Completion of the installation of the main set of windows and doors and also the installation of the ridge tiles on the roof over the Garages (taking advantage of a day of dry and not particularly windy weather).



Completion of the installation of the main set of windows and doors and also the installation of the ridge tiles on the roof over the Garages (taking advantage of a day of dry and not particularly windy weather).



Mortaring the last of the roof tile verges, on the West-facing gable of the Garage block – then some progress installing the guttering.
No further work on the mains electrical installation today but the separate team from the intruder and fire alarm contractor started their first-fix.