Week 32, Day 1

Week 32, Day 1:

  • Some showers at the end of the day, hence the rain-spots on the lens of the time-lapse camera
  • Good progress installing the majority of the ventilation ducts back to the plenum chambers in the Plant Room
  • Some preparatory work by Western Power Distribution for upgrading and re-routing the electricity supply cable from the transformer – they will be installing a larger cable and burying it underground
Week 32, Day 1

Week 32, Day 1

Week 17, Day 2

Week 17, Day 2:

  • Installation of the electricity supply cable between the GRP cabinet containing the electricity meter and the location for the main consumer unit (behind the door from the hall into the kitchen)
Week 17, Day 2

Week 17, Day 2

New electricity cable near the GRP cabinet

New electricity cable near the GRP cabinet

New electricity cable emerging from the underfloor void

New electricity cable emerging from the underfloor void