Week 47, Day 2

Week 47, Day 2:

  • Lots more work on the second-fix electrical, including the light fittings and drivers in the kitchen and the control panels for the ground floor
  • Further work on the interior woodwork (window sills) and door furniture
Week 47, Day 2

Week 47, Day 2

BPM AQUILAE recessed LED downlight in kitchen

BPM AQUILAE recessed LED downlight in kitchen

Control panels mostly complete for the Ground Floor

Control panels mostly complete for the Ground Floor

Week 45, Day 4

Week 45, Day 4:

  • MVHR commissioning by Steve from the Green Building Store, adjusting all the air valves to deliver the correct flow rates and setting the Low, Medium and High fan speeds
  • More second-fix on the intruder and fire alarm system, installing the control panel, keypad etc.
  • More second-fix electrical, including installing some of the wall lights
  • More work on the door furniture, including the lock on the Plant Room door
Week 45, Day 4

Week 45, Day 4

Intruder alarm box on the west elevation

Intruder alarm box on the west elevation