Week 2, Day 2

Week 2, Day 2:

  • Installation of the shuttering (wooden formwork) within the old cellar, ready to hold the foundation concrete while it sets – see second photo below
  • Completing the rest of the digging for the foundations, including adding the extra-wide areas for where the steel posts will connect to the concrete foundations and need extra support
Week 2, Day 2

Week 2, Day 2

Shuttering in old cellar

Shuttering in old cellar, at south-east corner of the new house

Week 2, Day 1

Week 2, Day 1:

  • Good weather which is forecast to continue for a week or more – cool overnight but lots of sunshine in the daytime
  • Site visit from the Architect at 08:00, likely to be a weekly event
  • More digging, getting more of the foundations down to the correct level
  • I decided where to locate the two Ground Source Heat Pump pipe trenches and marked out the line of the first one ready for digging
Week 2, Day 1

Week 2, Day 1