Week 6, Day 5 Posted on 2015-11-13 by dMb Reply Week 6, Day 5: Formal site meeting #1 with the project Architects, Justin Smith and David Crane. Completion of the back-filling of the soil between the internal walls ready for the oversite concrete, using an even smaller digger. Week 6, Day 5 Interior footprint almost ready for oversite concrete
Week 6, Day 4 Posted on 2015-11-12 by dMb Reply Week 6, Day 4: More progress on the below-floor internal blockwork walls. Week 6, Day 4 Interior walls approaching the level required to support the beam-and-block floor