Week 46, Day 4

Week 46, Day 4:

  • Progress on the floor and wall tiling, preparing the wet-room floor in the Ground Floor shower room and tiling in the Master Bedroom En-Suite
  • More work on the foul water drainage
  • Final preparations for the air pressure test (scheduled for tomorrow) – sealing the area where most of the pipes enter the building in the Utility Room, and fitting the Cat Flap
  • Commissioning the intruder and fire alarm systems – testing all the sensors and programming via the keypad
Week 46, Day 4

Week 46, Day 4

Week 46, Day 3

Week 46, Day 3:

  • Installing the inspection chambers (bedded in concrete) and the drainage pipes (bedded in pea shingle) to the east of the house
  • More second-fix plumbing, installing the wall-mounted WC in the Master Bedroom En-Suite and fitting some more shower riser bars and spray heads
Week 46, Day 3

Week 46, Day 3

Main run of foul water drainage; Biorock treatment tank in the distance

Main run of foul water drainage; Biorock treatment tank in the distance

Wall-mounted WC in Master Bedroom En-Suite

Wall-mounted WC in Master Bedroom En-Suite