Week 77, Day 3

Week 77, Day 3

  • More ‘finishing’ jobs outside and snagging inside
  • Sealing the joints between the concrete linear drainage units and installing the galvanised steel gratings on those (see photo)
  • Replacing one of the stainless-steel handrail tubes on the balcony which had started to corrode (must have been the wrong specification of stainless steel)
Week 77, Day 3

Week 77, Day 3

Galvanised steel gratings over linear drain at north side of house

Week 76, Day 5

Week 76, Day 5:

  • Another air pressure test following the work on the window and door seals on Tuesday.
    • The build team were hoping the replacement of the sliding door seals in particular would make a big difference (despite having taped over those seals during some previous tests wth minimal impact) but I wasn’t expecting a huge improvement.
    • The test came in at 0.9 ACH @ 50 Pa whereas Passivhaus Certification demands 0.6 or lower, so still more work to do.
  • Good progress on the 50m-long swale that will take the rainwater from the house roof and attempt to disperse it before allowing any excess to drain to the field ditch through a controlled outflow
  • More minor internal snagging items completed, including re-instating the end caps on the lower flight of stair treads
Week 76, Day 5

Week 76, Day 5

Partially completed swale to the west of the house