Outbuildings: Week 30, Day 1

Outbuildings: Week 30, Day 1

More groundworks in the Courtyard, this time with a focus on the ‘land drains’ nearer the house – including digging down to Courtyard level at the South-West corner.

Then also progress on the Brickwork and Blockwork for the External Staircase, for which the reconstituted stone steps are in the process of being wet-cast.

Progress on the supporting masonry for the external staircase, which has two openings beneath the steps

Outbuildings: Week 29, Day 5

Outbuildings: Week 29, Day 5

Further progress on the underground drainage in the Courtyard, this time with a focus on the ‘land drains’ which will address the tendency for the area to collect standing water (nicely evidenced in recent days).

One of the ‘land drains’ in the Courtyard

These ‘land drains’ consist of a perforated pipe wrapped in landscape fabric (to prevent silt infiltration) installed in a trench filled with pea gravel.

Work on the masonry continued with some progress on the supporting brick- and block-work for the external staircase.