Much less rainy today so decent progress erecting more of the scaffolding, and more insulation and blockwork on the right, where the scaffolding had been completed.

Much less rainy today so decent progress erecting more of the scaffolding, and more insulation and blockwork on the right, where the scaffolding had been completed.

The first properly wet day since work started – which isn’t bad for 12 weeks. The rain proved problematic for using a new (so very wet) batch of ready-mixed mortar, so work stopped early.
Some progress with the scaffolding, though again slowed down by the rain.