Outbuildings: Week 24, Day 2

Outbuildings: Week 24, Day 2

More progress on the roof tiling – above and to the left of the solar PV array.

Roof tiling completed around the solar PV array and progressing towards the West gable of the South-facing roof

Multiple deliveries too – another 2,000 roof tiles and the rainwater goods.

Then also the first day of first-fix on the electrical installation.

Outbuildings: Week 18, Day 4

Outbuildings: Week 18, Day 4

Another very hot day making for difficult conditions on-site. Nevertheless, the team continued to progress the walling and the roof structure.

Also a site visit from the electrical contractor to discuss a few points about the sizing of the supply cabling and to review the layout of the buildings.

It looks like a spider has built a web over the lens of the time-lapse camera which takes the daily overview photos – there’s a dark shadow at the top-middle, more evident early in the day. The other cameras have Infra-Red LEDs for night-time usage but those are turned off on this camera (because they’d never manage to illuminate the whole courtyard) in an attempt to discourage web-building. Perhaps a strong wind will blow that off; if not the lens will need cleaning.