Week 52, Day 5

Week 52, Day 5:

  • The most notable progress today was the installation of the oak boxes over the steel treads on the upper flight of stairs
Week 52, Day 5

Week 52, Day 5

Oak stair boxes installed on first-to-second floor staircase

Oak stair boxes installed on first-to-second floor staircase

Week 52, Day 3

Week 52, Day 3:

  • More preparation for installing the oak boxes on the stairs
    • Plastering the patches done yesterday
    • Cutting the plasterboard from around each tread, so that the slight movement in the treads doesn’t move the plasterboard
  • Some finishing off of the ceramic wall tiles in the bathrooms
Week 52, Day 3

Week 52, Day 3

Upper flight of stairs patched ready for oak boxes

Upper flight of stairs patched ready for oak boxes