Week 35, Day 1

Week 35, Day 1:

  • Lots more rain
  • The main event for the day was the installation of the “missing” window on the second floor and the replacement of the two windows originally made with the wrong colour frames
  • More electrical first-fix
  • Installing some of the contoured panels for the LED strip lights recessed into the ceiling
Week 35, Day 1

Week 35, Day 1

Lifting the glass for the Office window up to the second floor

Lifting the glass for the Office window up to the second floor

Office window installed on the second floor

Office window installed on the second floor

"Fylo" lighting channel installed in the ceiling - needs another layer of plasterboard to bring it flush

“Fylo” lighting channel installed in the ceiling – needs another layer of plasterboard to bring it flush

Week 34, Day 5

Week 34, Day 5:

  • Some very heavy rain showers, hence the generally-damp look and the muddy puddles
  • The Ground Source Heat Pump and its accompanying tanks were delivered ready for installation next week
  • Some more electrical first-fix, mostly low-voltage cabling to the LED down-lighters from their (remote) drivers
  • Battening out the Master Bedroom walls and (sloping) ceiling ready for plasterboard – see photos below
Week 34, Day 5

Week 34, Day 5

"3x2" battens on the sloping ceiling of the master bedroom

“3×2” battens on the sloping ceiling of the Master Bedroom

The battens on the ceiling need to provide clearance for some low-profile downlighters.

Slim battens on the north wall of the Master Bedroom

Slimmer battens on the north wall of the Master Bedroom