Week 30, Day 3

Week 30, Day 3:

  • Delivery of the lighting fixtures required for first-fix, where they need to be incorporated into the plaster on the walls or ceilings
  • More electrical first-fix, including cabling the control points for the electric windows and blinds
  • More plumbing first-fix, including installing the pipework for the bath fillers and the digital shower control boxes
Week 30, Day 3

Week 30, Day 3

First-fix wiring for electric windows and blinds

First-fix wiring for electric windows and blinds

Mira Platinum digital shower mixers

Mira Platinum digital shower mixers

Week 30, Day 2

Week 30, Day 2:

  • The first really wet day in several weeks
  • More first-fix, electrical and plumbing
  • Insulation and air-tight taping around the steelwork in the southern bedrooms
Week 30, Day 2

Week 30, Day 2

Insulating the steel beam in the second bedroom

Insulating the steel beam in the second bedroom

The pro clima Contega PV tape will get plastered into place to form an air-tight barrier.