Week 29, Day 2

Week 29, Day 2:

  • Fixing the zinc roof panels under the eaves on the eastern elevation, so now the cedar cladding can go on that side
  • Lots more first-fix, electrical and plumbing
Week 29, Day 2

Week 29, Day 2

Zinc panels under the eaves on the eastern elevation

Zinc panels under the eaves on the eastern elevation

Partial first-fix for the front door control unit

Partial first-fix for the front door control unit

The Paxton Net2 control unit for the front door needs surprisingly many connections:

  • A mains feed via a fused spur
  • An Ethernet connection to link back to the server PC, for programming
  • A connection out to the door, to lock/unlock it
  • A connection to the intruder alarm, for arming/disarming the alarm via a key fob
  • A connection to the door intercom, so that can also unlock the door (remotely)

Further connections, required but not yet installed:

  • The external proximity reader
  • The internal proximity reader
  • The 24DC power supply for the door lock

Week 28, Day 5

Week 28, Day 5:

  • The first section of cedar cladding installed on the southern end of the east elevation
  • Continuing to prepare the second floor for plasterboard, installing the vapour-tight membrane under the roof and an air-tight membrane on the gable walls, then installing battens to form a service void and to take the plasterboard
  • More first-fix plumbing and electrical
Week 28, Day 5

Week 28, Day 5

Wider view from main camera location

Wider view from main camera location

First section of cedar cladding on eastern elevation

First section of cedar cladding on eastern elevation

Office with vapour and air tight membranes

Office with vapour and air tight membranes