Week 27, Day 4

Week 27, Day 4:

  • Still more first-fix
  • Starting to install the black membrane that goes over the outer skin of block-work (and over the insulation on the outside of the SIPs on the gable walls), together with the vertical timber battens that will hold the horizontal cedar boards over the first- and second-floor walls
Week 27, Day 4

Week 27, Day 4

Black membrane and vertical battens on east wall

Black membrane and vertical battens on east wall

Close-up of membrane and vertical battens

Close-up of membrane and vertical battens

 

Week 27, Day 3

Week 27, Day 3:

  • Installation of the Ecobead Platinum cavity wall insulation
  • The start of the preparation of the Western Red Cedar cladding boards
    • These get a coat of Osmo Clear UV-Protection Oil Extra (420 Clear Semi-Matt) before being installed
  • Completion of the external insulation on the gable walls of the Structural Insulated Panels
  • More first-fix of plumbing and electrical systems
Week 27, Day 3

Week 27, Day 3

Cavity Wall Insulation lorries

Cavity Wall Insulation lorries

Western Red Cedar timber cladding being prepared for installation

Western Red Cedar timber cladding being prepared for installation

Osmo UV Protection Oil

Osmo UV Protection Oil