Week 30, Day 4

Week 30, Day 4:

  • More first-fixing
  • Plastering-in the air-tight tape on the southern bedroom walls, where these will get plasterboard rather than a wet plaster finish (which normally forms the air-tight layer)
  • More work on the studwork walls – especially on the second floor where the plasterboard will get installed first
Week 30, Day 4

Week 30, Day 4

Air-tight tape now plastered into place in master bedroom

Air-tight tape now plastered into place in master bedroom

Studwork wall in second floor bathroom

Studwork wall in second floor bathroom

Week 28, Day 4

Week 28, Day 4:

  • A wetter day, so more work inside than outside
  • More work on preparing the second floor for plasterboard
  • More first fix of electrical and plumbing
Week 28, Day 4

Week 28, Day 4

Partition wall between Plant Room and double-height Master Bedroom

Partition wall between Plant Room and double-height Master Bedroom

Example of hot and cold water pipework

Example of hot and cold water pipework

The hot water pipework to basins is 12mm Uponor MLCP with black Armaflex insulation. The aluminium layer in the MLCP sandwich means these pipes tend to stay where they’re bent to – hence the ends tend to be straight rather than curly. The cold water pipework isĀ  standard 15mm PEX with grey Climaflex insulation; no aluminium layer.