Week 42, Day 3

Week 42, Day 3:

  • Some more work on the zinc roof though progress was restricted by the strong and gusty wind – not compatible with manipulating 4m x 0.5m lengths of zinc sheeting at height
  • Good progress on the cedar cladding for the reveals around the windows on the south side of the first floor, where the scaffolding will be removed in a couple of days
  • Applying the protective oil to the cedar cladding most recently installed – e.g. the window reveals and around the balcony
  • More second-fix plumbing, including the supply and waste connections for the kitchen sink and dishwasher – easier before the worktops are installed – and the twin washbasin the the Master Bedroom En-Suite
  • More second-fix electrical, mainly the isolators for the various kitchen appliances
  • More plastering, mainly in the Hallway
Week 42, Day 3

Week 42, Day 3

The start of the final section of the north roof, east of the rooflights

The start of the final section of the north roof, east of the rooflights

Window reveals and sills on the first floor, south side

Window reveals and sills on the first floor, south side

Doors installed on integrated fridge and freezer

Doors installed on integrated fridge and freezer

Plaster in the Hallway

Plaster in the Hallway

Twin washbasin in Master Bedroom En-Suite

Twin washbasin in Master Bedroom En-Suite

Week 42, Day 1

Week 42, Day 1:

  • The team from Full Metal Roofing were back on-site and completed about half of the zinc roof covering on the curved section of the north roof
  • More plastering, including the Hall ceiling and the Balcony ceiling
  • Trimming back the cedar cladding around the first- and second-floor windows ready for boards on the reveals and the window sills
  • Marking out the kitchen ceiling ready for the in-ceiling loudspeakers
  • (Actually on Saturday): Transporting the bespoke (extra-tall) interior doors from the builders’ workshop to site
Week 42, Day 1

Week 42, Day 1

Working on the zinc over the curved section of the north roof

Working on the zinc over the curved section of the north roof

Plastered ceiling above the first-floor balcony

Plastered ceiling above the first-floor balcony

Mira shower in second bedroom en-suite

Mira shower fittings in second bedroom en-suite

Bespoke interior doors temporarily stored in Living Room

Bespoke interior doors temporarily stored in Living Room