Week 65, Day 5

Week 65, Day 5:

  • More work on the door canopies, mostly the side door since the front door is nearing completion
  • Installation of the flat panel lights in the ceilings of the door canopies, to illuminate the area outside the doors
Week 65, Day 5

Week 65, Day 5

Side door canopy with some of the cedar cladding installed

Front door canopy with light installed

15W LED flat panel over front door

Week 49, Day 2

Week 49, Day 2:

  • More issues with the automated WordPress updates – I did a WordPress upgrade at the weekend and forgot to check whether wp-cli (which does most of the work for the automated daily updates) needed an update too (it did)
  • The final delivery of BPM light fittings from Phil at GreyBlue with some of them installed already – notably the two LUK CRUSADER which at 120mm in diameter seems enormous close-up but it’s a powerful fitting (30W of LED running at 900mA) and so only really suitable for large-scale installations
  • More work commissioning the internal and external wall-lights which are (mostly) simply switched rather than being on dimmer controls
    • These are controlled by a multi-channel KNX relay (not via DALI) and so need commissioning in KNX and some sort of user interface for control
    • After work I got a simple configuration working in OpenHab to be able to test these lights and they all work fine – I find it very pleasing to stand outside with a smartphone and turn the external floodlights on and off over WiFi
  • The main “nerve centre” in the Dressing Room on the First Floor is now nearly complete – just a few more switches to go
  • Off-site work by Mick machining the oak boxes for the staircase treads at the workshop
Week 49, Day 2

Week 49, Day 2

BPM LUK CRUSADER lamp over the staircase

BPM LUK CRUSADER lamp over the staircase

BPM IKI Wall Lights in the Dining Room

BPM IKI Wall Lights in the Dining Room

Control boards in the Dressing Room on the First Floor

Control boards in the Dressing Room on the First Floor