Week 49, Day 5

Week 49, Day 5:

  • At the moment a lot of the progress doesn’t show up in the pictures – there’s quite a lot of “soft” configuration of the lighting, security and heating systems where it doesn’t look like anything has changed
  • Since there’s a duct heater on the MVHR Supply to the house, the ducts down-stream of this need to be insulated to keep the heat inside the ducts so the air is still warm when it gets to the far end
    • The “hot” water supply to the duct heater is coming from the Ground Source Heat Pump and is therefore going to be warm rather than hot with most likely a relatively small effect on the air temperature
    • The small-bore plastic heating ducts are naturally better insulated than steel ducting and these were intentionally enclosed in the inter-floor insulation (more intended for acoustic rather than thermal purposes) so it’s really just the steel ducts and plenums in the Plant Room that need insulating
  • More work commissioning the lighting systems
    • Now all of the internal downlights and wall lights are installed and working, with just the LED strip lights and most of the outside lights to go
    • In the evening I completed the basic KNX programming so that the ceiling-mounted PIR switches in the bathrooms and hallways / landings control the relevant lights and the relatively small number of wall switches control the main lights in each room
    • The Up/Down light on the Balcony (a Nordlux Canto Maxi) has a pair of (allegedly) dimmable 5W GU10 LED bulbs controlled by an Aurora AU-DATR400 mains-voltage DALI dimmer. Compared to the excellent dimming behaviour of the internal lights with their separate DALI dimmers this combination isn’t anything like as good. More investigation required.
Week 49, Day 5

Week 49, Day 5

Partially-completed lagging on the ventilation ducts downstream of the duct heater

Partially-completed lagging on the ventilation ducts downstream of the duct heater

Balcony Up/Down Wall Light

Balcony Up/Down Wall Light

Week 49, Day 3

Week 49, Day 3:

  • Almost completed on the Ground Source Heat Pump commissioning – all powered up and heating water with just a bit more insulation to finish off
  • Installing the hand rail for the balcony, ready for the glass balustrade
  • More second-fix electrical, connecting up the electric windows on the second floor and more of the wall lights
Week 49, Day 3

Week 49, Day 3

Handrail installed for balcony; just the glass to go

Handrail installed for balcony; just the glass to go

Electric clerestory windows on the second floor

Electric clerestory windows on the second floor

Master bedroom wall lights when illuminated

Master bedroom wall lights when illuminated