Week 17, Day 4 Posted on 2016-02-11 by dMb Reply Week 17, Day 4: Mostly a day of preparing the site ready for the roof structure installation next week Week 17, Day 4
Week 17, Day 3 Posted on 2016-02-10 by dMb Reply Week 17, Day 3: Completion of the last section of the second floor structure, over the balcony in the south-west corner Week 17, Day 3 Second floor structure and boards above balcony Edge of floor structure over balcony