Week 69, Day 3 Posted on 2017-02-22 by dMb Reply Week 69, Day 3: More work on the stone cladding and the waterproofing for the door canopies Week 69, Day 3 Capping around the waterproof membrane over the front door canopy
Week 69, Day 2 Posted on 2017-02-21 by dMb Reply Week 69, Day 2: More work on the stone cladding More work on the waterproof coverings for the door canopies Installation of shower screens in 3 of the bathrooms by Alvaston Glass (that’s their van in the photo) Most of the work is complete but there are some loose ends to sort out in a few days – like hanging the shower doors Week 69, Day 2 Shower screen in Bedroom 2 En-Suite