Week 80, Day 1

Week 80, Day 1:

  • The team from Full Metal Roofing were back on site to prepare for the installation of the zinc covering for the “window boxes”. They will now prepare the zinc sections in their workshop ready for installation later in the week.
Week 80, Day 1

Week 80, Day 1

Zinc underlay for Living Room “window box”

Zinc underlay for Dining Room “window box”

Week 79, Day 1

Week 79, Day 1:

  • Having completed all they can for now, the build team are off-site again while awaiting the availability of the zinc roofing contractors to start work on the zinc around the ground-floor windows.
  • I’m going to keep the automatic daily blog updates happening for now and then I’ll delete the ones when nothing special happens.
Week 79, Day 1

Week 79, Day 1