Week 78, Day 1

Week 78, Day 1:

  • After 15 weeks off-site working on other projects, Burton Building Solutions are back to complete their remaining work. This is the 78th week of active building on-site, excluding any non-working weeks. Automatic daily updates are now resumed.
  • The most obvious outstanding item is the zinc cladding around two of the ground-floor windows (replacing the black plastic) but there are several more minor items to complete as well, plus some defects that need attention.
  • Progress today including removing the supporting battens from under the stone cladding and tidying up the removal of a row of blocks from the planting beds on the north side.
Week 78, Day 1

Week 78, Day 1