More progress on tiling the roof. The West-facing section of the Workshop roof is completely tiled (except for the ridge) and the North-facing section of the Utility Room roof was mostly complete by the end of the day.
The plan is to continue around the back of the buildings, leaving the area that will receive the recessed solar panels until last – allowing time for the (separate) team who will be installing those to schedule their time on site.
The Barn Door, Stable Door and Stable Window were delivered by Monarch Equestrian. Those won’t be able to be installed until the scaffolding comes down.