Week 72, Day 1 Posted on 2017-03-13 by dMb Reply Week 72, Day 1: The main build team will be off site for a few weeks but some of the subcontractors are continuing to work, notably on the stone cladding Week 72, Day 1 Completed stone cladding on western elevation First few courses of stone cladding on the north west corner
Week 71, Day 5 Posted on 2017-03-10 by dMb Reply Week 71, Day 5: A little bit of progress on the stone cladding but overall not much to report Week 71, Day 5