Outbuildings: Week 29, Day 2

Outbuildings: Week 29, Day 2

Good progress with the rainwater drainage around the Courtyard. Further progress with the first-fix plumbing. Plasterboarding of the ceiling over the Workshop and Utility Room now completed, along with the first 100mm of loft insulation (laid between the ceiling joists) – enabling the start of work on the MVHR ventilation ducts.

Outbuildings: Week 29, Day 1

Outbuildings: Week 29, Day 1

More good weather; the large puddle in the Courtyard has mostly dried up.

The trench required to install the ducts for the electrical supply cables (using the digger visible at the-top-right of the overview photo) was dug and back-filled.

The scaffolders were back, dismantling all the remaining scaffolding and removing most of it off-site.

The plumbers started their first-fix, making good progress running pipes around the inside of the building.

The main build team concentrated on installing more of the plasterboard ceiling and fitting the first layer of insulation above that.